We are working in a Project, where the client wants
1. To put the operation in the inspection plan and that automatically the master characteristics are created, for my understanding is kind of a master operation, in the master operation you defined the characteristics you want to copy, do you know a standard or not standard way to do it
2. Also they want to create the inspection points automatically for example when they create the fabrication order
Any suggestion is welcome
Thanks in advance