Shop Papers via Mail to Customer / Vendor
Hi Via Standard is it possible to send the Shop paper of Notifications (as an attachment) to customer or Vendor.
View ArticleCatalog Long TEXT to be copied Automatically in Notification
Hello Gurus, We have maintained TEXT (Questionare which will help assigned user / department to take up the issue further) in Catalogs (Type 02) .Now when ever we have NC is plant user selects...
View Articleformula for MIC in inspection plan
Hello Experts, I have to use formula like Max(MIC1615 and MIC1616) for MIC 1617 in inspection plan.How can I implement this formula in inspection plan? Please guide me Thanks in advance Best...
View ArticleInspection lot currently prevents a quantity change in HU item
When i try to do PGI it says Inspection lot currently prevents a quantity change in HU item When i check the lot the error message is The handling unit assigned to delivery cannot be processed Can...
View ArticleCan't create an outbound Quality Cert using QC20
Hi Gurus, I have a situation where I am generating a Quality Cert with no issue from Plant A, which produced the product and shipped it as well. This works fine. Now I have anther producing plant...
View Article0130 inspection prefered insp type setting --for Semi finished Product.
Hi Experts, Semi finished (SM1 ) material is having One BOM component as (RM1). The SM1 is : a)Produced in House b)Procured from Vendor against Purchase orders. c)Procured from Subcontracting Process...
View ArticleInspection plan not assigned to inspection lot
Hello Experts, I am getting message when i am trying to click on usage decision in QA32 transaction as below- Characteristic results cannot be recorded for inspection lot XXXXXX I see that my...
View Article8 D Report
Hello Gurus, I tried two options for 8D in Notification 1. Via Action Box - Layout get generated but its just blank. task , cause etc are not getting reflected in layout.2. Via Shop paper - Its is not...
View ArticleStandard setting for inspection lot.
Hi experts, Can you please let me know is there any setting exist for inspection lot, if an user will go to do the usage decision of an inspection lot without completing the results recording then...
View ArticleNo results confirmation exists for inspection unit
Hi, While recording the results, I'm getting this message.Please let me know,if i miss anything. No results confirmation exists for inspection unit 13052016165Message No. QE039 For characteristic, this...
View ArticleBapi to change the workcenter for CRQ2
Hi Experts,I want to change record for CRQ2 using function module. I found one FM CRAP_WORKCENTER_CHANGE. I passed the inputs and i tried to change the description IN_CRHD_API01-ktext = 'sample text'...
View ArticleInspection lot status change from REL to LTCA
Dear Experts, I have Inspection lots with IL Origin 01 and Stock already Moved from QI due to 102 movements But Lot is still open in REL status. Do you have any IDEA About Functional Module to Change...
View Articleassign multiple sales order to a quality notification
Hello Experts, I have a scenario wherein the customer wants a Credit note and a Return order to be created for a Quality notification. this is being done using a Function Module ZQM_NOTIF_ORDERS....
View ArticleBatch not updated in Inspection lot
Hi, I have come across one issue that batch is not updated in the Inspection lot. We are posting inbound delivery for the goods receipt. At the time of inbound delivery, system creates batch and once...
View ArticleRequired Characteristics still open, want Force inspection completion ?
Hi I entered results using QE51n, saved and on entering UD, the system says "Required Characteristics still open, Do you want Force inspection completion ?" Though I have entered valuation /...
View ArticleWebservices for Creating SNNs & Reading SNN Deatils
Hello, We are in the process of integrating our service notification portal with SAP. The portal basically creates service notifications in SAP (IW51). The current process depends on file based...
View Article0130 inspection prefered insp type setting --for Semi finished Product.
Hi Experts, Semi finished (SM1 ) material is having One BOM component as (RM1). The SM1 is : a)Produced in House b)Procured from Vendor against Purchase orders. c)Procured from Subcontracting Process...
View ArticleReleasing GR Blocked Stock to any unrestricted storage location
We have some stocks in non-valuated GR blocked stock which was posted from Purchase Order with movement type 103Now, the decision is to dispose the material. We have dedicated scrap location in system....
View ArticleCertificate of Analysis Process
Hi QM Exports, i need step by step process of COA in QM, Can any body help me for same. Payal Gupta
View ArticleQS27 - Fill in all required entry fields
Hello Gurus, I want to replace a MIC by an other. MIC with QS27. When I select a ligne and I do "Start replacement F8" : I have an issue : I don't understand why I have this message, and why it does...
View Article