Hello Team,
Please guide me to overcome below issue.
Configuration done:
1.Defined Task code Priorities in 'Response profile - Response Times' as below.
as initial case requirement discussed with only based on 'Task finish days', all are set & working in line as shown in below.(MM/DD/YY)
Task code QN-ZM1 startdate is default as Today + interval 5 days=3/15/20016
Task code QN-ZM2 startdate is default as Today + interval 30 days=4/10/20016
Task code QN-ZM3 startdate is default as Today + interval 5 days=3/15/20016
Now the requiremnt has changed to adjust the task code start dates as : First task code end date is start date of Second Task code.(MM/DD/YY)
Task code QN-ZM1 startdate is 03/10/2016 + interval 5 days=3/15/2016
Task code QN-ZM2 startdate is 03/15/2016 + interval 30 days=4/15/2016
Task code QN-ZM3startdate is 04/15/2016 + interval 05 days=4/20/2016
Please advice.
Thanks in advance,
Karthik